Customize your Project Plan
by tailoring Smartsheet
o We need to perform a "Feasibility Study" to define, which material, which
equipment and which work steps and effort will be necessary to manufacture
the product later.
Special demand: Since we are certified according to IATF 16949, the partici-
pants of the cross-functional team who will perform the Feasibility Study
should also "sign and confirm" it.
o Based on the Feasibility Study, a "Cost Estimate" will be created to determine
the selling price.
o Our customer demands in their RFQ (Request for Quotation) a mandatory
"Due Date" because they would like to present the parts at a trade fair.
o Then we send our quotation and expect from the customer their "Purchasing
Order".
Then the Project Phase begins:
o Project "Kick-Off" and introducing the project team members.
o "Designing" the parts.
o "Material procurement", concerning in-house as well purchasing from suppli-
ers.
Part Number Part Name DE Part Name EN Lead Time Supplier
P1001.01.00 Oberteil Upper Housing 2 weeks In-house
P1001.02.00 Unterteil Bottom Housing 2 weeks In-house
P1001.03.00 Leiterplatte Conductor Board 4 weeks HAP Power
P1001.04.00 Vordere Abdeckung Front Cap 2 weeks In-house
P1001.05.00 Hintere Abdeckung Hind Cap 2 weeks In-house
o Manufacturing and "Assembly" of the parts.
o An "Alternating Climate Test" according to our Design Verification Plan
(DVP/R) through 8 consecutive days.
o "Shipping" the parts to the customer.
Task: Let's plan and monitor the project successfully!