Page 54 - Customize-Project-Plan-by-tailoring-Smartsheet
P. 54

Customize your Project Plan
                                                                                                            
                                                                               by tailoring Smartsheet


               Next question: How do we define a "Solid Milestone"?

               Answer:

                          a)  We assign the task a duration of zero (0) days,


                          b)  and enter the date directly in the column "Start". Because Duration is 0 days, Smart-
                              sheet also writes in the column "Finish" then the same date as at "Start".


                          c)  A "Solid Milestone" has no predecessor that refers to a task in the schedule. To accom-
                              plish this, keep the cell at the predecessor column empty.


               Let's continue …

                   Do we want to set another milestone?

                   We could do that if we believe that the "Order by Customer" (row 7) is a distinct point in our
                   project. Or we could decide to declare the "Project Kick-Off" (row 9) as a milestone? Let's say, we
                   decide for the Kick-Off as a milestone. See, it's up to you to declare certain points in the project as
                   a milestone.

                   Question: Is this a "Floating Milestone" or a "Solid Milestone", either?

                   Answer:

                   This is a "Floating Milestone" because the date would change, if, for example, the durations of the
                   previous activities (rows 3 through 7) would change, or if the task relationships ("Predecessors")
                   would change.

                   Or in other words, at this milestone is a "predecessor" assigned, so it's easy to recognize that this
                   is a "Floating Milestone".
































               © Hans Porzel, 10/2025 | CAPM® (PMI), PSM I® (Scrum.org), Smartsheet Prod. Cert® 2020                                             Page 54 / 209 pages
   49   50   51   52   53   54   55   56   57   58   59